Project Timeline
Date |
Milestone |
2005 |
|
Sept |
Waveney Campus Project (WCP) partnership is created Feasibility study carried out and potential sites in and around Lowestoft identified |
Dec |
EEDA joins the Project Board |
2006 |
|
Feb |
Initial contact made with landowners at the site to outline general details of the project |
March |
Possible sites narrowed down to two – the former Shell base at Commercial Road and the Riverside Business Park |
April |
Suffolk County Council confirm commitment to WCP at a Cabinet meeting |
May |
Negotiations with land owners formally opened |
June |
Defra gives full backing to the project with a Ministerial announcement by Lord Rooker, the Minister responsible for Defra’s laboratory strategy plans |
July |
Decision is made on the most suitable site for Waveney Campus. The Waveney District Council Executive Committee agrees to progress with plans to acquire the site Architects appointed |
August |
Waveney District Council formally approves the compulsory purchase order (CPO) for the land on the agreed site |
Oct |
Design work begins |
Nov |
The CPO is issued to landowners |
Dec |
Objections to the CPO received by Waveney District Council 1st East join the project board |
2007 |
|
Jan |
Project board signs-off the Outline Business Case (OBC) Procurement strategy agreed and loan funding confirmed Public inquiry plan announced |
Feb |
Office of Government Commerce confirms the project is affordable and value for money; the OBC is considered a model of best practice |
April |
OJEU (procurement) notice goes out Public inquiry begins 17th April |
June |
Public inquiry reconvenes but is adjourned to enable redrafting of the laboratories; some land unlikely to be needed |
Oct |
Public inquiry reconvenes and concludes after land objections are withdrawn |
2008 |
|
Jan |
Public Consultation |
Feb |
Submit planning application |
Nov |
Enabling works start on site |
2009 |
|
Spring |
Construction begins |
2010 |
|
Sept |
Construction completed |
Autumn |
Occupation of the building |